Success Milestones
2014
April 27, 2014
Achieved ICMAB Best Corporate Award – 2013
January 21, 2014
Signed Term Loan of USD 21.975 million funded by the World Bank for BPPL
2013
November 1, 2013
Signed Flue Gas Desulfurization (FGD) Equipment purchased contract for BPPL
August 29, 2013
Sanctioned Term Loan of USD 04 million by IDCOL
March 20, 2013
Signed Syndicated Term Loan facility of BDT 2,205 million for BPPL
January 12, 2013
Achieved Best Corporate Award – 2012 from ICMAB
2012
February 15, 2012
Exhaust Gas Secondary Power Plant Supply Contract with Greens Power Ltd, UK for BPPL
January 24, 2012
Sub Station Equipment Supply Contract with Siemens Bangladesh Limited for BPPL
2011
October 19, 2011
Gen Set Supply Contract with Rolls Royce Marine AS, UK for BPPL
July 31, 2011
Signed an agreement with BPDB to build a 50 MW Power Plant at Patenga, Chattogram by formation of new company named Baraka Patenga Power Limited (BPPL)